Goleniów-Lwówek gas pipeline

The project will consist in the construction of a new Goleniów-Lwówek gas pipeline along the existing Szczecin-Lwówek gas pipeline (red line).

goleniow-lwowek_mapa_ENG_www

Description

  • location – the pipeline will be built in three voivodeships: Zachodniopomorskie, Lubuskie and Wielkopolskie, in the communes Goleniów, Maszewo, Stargard Szczeciński, Dolice, Przelewice, Pełczyce, Strzelce Krajeńskie, Zwierzyn, Santok, Deszczno, Skwierzyna, Przytoczna, Pszczew, Międzychód, Lwówek
  • Pipeline length: approx. 188 km
  • The pipeline construction will be carried out in two stages:
    • stage I: section of the Goleniów-Ciecierzyce gas pipeline – approx. 117 km
    • stage II: section of the Ciecierzyce-Lwówek gas pipeline – approx. 71 km
  • Nominal gas pipeline diameter – DN 1000 mm

Schedule

  • 1st quarter 2020 – obtaining the building permit
  • 3rd quarter 2022 – construction completion date

Key facts

- estimated length

188 km

– estimated length
- diameter of the gas pipeline

1000 mm

– diameter of the gas pipeline
- operating pressure

8,4 MPa

– operating pressure

Engineering contractor

MGGP S.A.

MGGP S.A.

Schedule

2020 - obtaining the building permit2022 - construction completion date
2020 – obtaining the building permit

2022 – construction completion date