Goleniów-Lwówek gas pipeline

The project will consist in the construction of a new Goleniów-Lwówek gas pipeline along the existing Szczecin-Lwówek gas pipeline.

Description

  • location – the pipeline will be built in three voivodeships: Zachodniopomorskie, Lubuskie and Wielkopolskie, in the communes Goleniów, Maszewo, Stargard Szczeciński, Dolice, Przelewice, Pełczyce, Strzelce Krajeńskie, Zwierzyn, Santok, Deszczno, Skwierzyna, Przytoczna, Pszczew, Międzychód, Lwówek
  • Pipeline length: approx. 188 km
  • The pipeline construction will be carried out
  • in two stages:
    • stage I: section of the Goleniów-Ciecierzyce gas pipeline – approx. 117 km
    • stage II: section of the Ciecierzyce-Lwówek gas pipeline – approx. 71 km
  • Nominal gas pipeline diameter – DN 1000 mm

Schedule

  • 1st quarter 2020 – obtaining the building permit
  • 3rd quarter 2022 – construction completion date

Engineering contractor

  • MGGP S.A.