Gustorzyn gas compressor station

The investment will consist in the construction of gas compressor station and the expansion of the installation constituting a part of the existing System Point in Gustorzyn.

gustorzyn_mapa_ENG

Project description 

Construction of Gustorzyn gas compressor station is directly related to the implementation of the Baltic Pipe project. The project will also involve the construction of new gas pipelines and extension of the two existing gas compressor stations in Odolanów and Goleniów.

Construction of the Gustorzyn compressor station is also partially related to the project of the interconnection between the transmission systems of Poland and Lithuania.

  • Target capacity of the gas compressor station: 30 MW (1st stage – 20 MW, 2nd stage – 10 MW).
  • Location: Brześć Kujawski Commune, Kujawy-Pomerania Province.

Schedule

  •  2019 – obtaining the building permit
  • 2022 – construction completion

Engineering contractor

  • PGNiG GAZOPROJEKT S.A.

Engineering contractor

PGNiG Gazoprojekt  S.A.
PGNiG Gazoprojekt S.A.

Schedule

2019 - obtaining the building permit2022 - construction completion date
2019 – obtaining the building permit

2022 – construction completion date